Examples · Walkthrough

On record before it’s covered

Follow a groundworks gang through the day they pour a concrete base: labour and plant recorded once, the reinforcement photographed before it is covered, the concrete matched to its ticket, one soft spot recorded as it was found, and the office’s view at the end of the day.

ExampleIllustrative workflow · fictional site data

Illustrative only, with fictional data. This shows record-keeping, not engineering, safety or contractual advice. Your contract, your client’s requirements and your own competent people decide what you record.

Interactive walkthrough

How the walkthrough works

Six short chapters follow one groundworks gang through the day they pour a concrete base, from the morning diary to the office’s view at the end of the day.

Guided playback takes about a minute and a half. You can pause at any time, choose a chapter, or take each step yourself.

  1. The day starts on the record
  2. Hidden works, before they are hidden
  3. Cleared to pour
  4. Something unexpected
  5. End of the day
  6. The commercial view

Prefer to read? The illustrated version tells the same story with stills and the interface details.

ExampleIllustrative workflow · fictional site data

Illustrated version

The same day, in six chapters

Stills from the 3D scene, what happens in each chapter, and what the site engineer’s tablet and the office monitor show. It needs no graphics support and works without JavaScript.

ExampleIllustrative workflow · fictional site data. Nothing here is a live system or a real site.

  1. Chapter 01 of 06

    The day starts on the record

    The gang at Plot 4: the site engineer holding a tablet, a groundworker kneeling at the edge of Base B2 behind barriers, Base B1 with its timber formwork, reinforcement cage and capped starter bars, and the site manager in the cabin behind.
    The gang, the plant on site and the day’s tasks, recorded once.

    Morning at Plot 4 on Job 2417. Base B1 is dug, blinded, shuttered and reinforced, ready for its pour. Base B2 is being dug out next to it.

    At 07:30 the site engineer opens the daily diary on a tablet: the ganger and the groundworker, the engineer, the site dumper, the plate compactor and the poker vibrator, and the two tasks for the day. Labour and plant are recorded once, here.

    Everything in this walkthrough is illustrative. The job, people, plant, tickets, quantities, times and dates are fictional.

    Show the screen

    Groundworks siteSite engineer’s tablet

    Site diary

    Diary · Tue 14 Oct

    Job 2417 · Plot 4 bases

    Status: Labour and plant recorded

    Plot 4 bases · Dry, 11 °C

    Gang
    • Ganger · DMOn site 07:30
    • Groundworker · RSOn site 07:30
    • Site engineer · AKOn site 07:30
    Plant on site
    • D-07 Site dumperOn site 07:30
    • PC-02 Plate compactorOn site 07:30
    • PV-01 Poker vibratorOn site 07:30
    Tasks
    • Base B1 · check and pourEngineer, gang
    • Base B2 · dig to formationGang

    Recorded once. Reused at the end of the day.

    The daily diary, with labour and plant recorded once.

  2. Chapter 02 of 06

    Hidden works, before they are hidden

    Close to the site engineer’s tablet: the pre-pour check for Base B1, five items each with a photo, initials and a time, and three photo slots filled.
    The formation and the reinforcement, photographed before the concrete covers them.

    Once concrete goes in, nobody can see the formation or the reinforcement again. So the pre-pour check for Base B1 is recorded while they are still visible.

    The site engineer photographs the formation and blinding at 09:10, then the reinforcement cage, its spacers and the starter bars at 09:16. Each of the five checklist items is recorded with a photo, the engineer’s initials and the time.

    Show the screen

    Groundworks siteSite engineer’s tablet

    Site diary

    Pre-pour check B1

    Job 2417 · Plot 4 bases

    Status: Awaiting sign-off

    Checklist · photo, initials, time
    • FormationPhoto · AK · 09:10
    • BlindingPhoto · AK · 09:11
    • ReinforcementPhoto · AK · 09:16
    • Cover spacersPhoto · AK · 09:17
    • Formwork and starter barsPhoto · AK · 09:18
    Photos
    • FormationTaken 09:10
    • ReinforcementTaken 09:16
    • Starter barsTaken 09:17

    The site engineer selects “Sign off pre-pour check”.

    Recorded before the concrete covers it

    The pre-pour check, each item with a photo, initials and the time.

  3. Chapter 03 of 06

    Cleared to pour

    The mixer truck parked beside Base B1, its drum turning and its chute swung over the formwork, with the pour under way.
    A signed pre-pour check, then the concrete matched to its ticket.

    At 09:40 the site engineer signs off the pre-pour check, and Base B1 is cleared to pour.

    The mixer truck arrives at 10:25. Its delivery ticket, DT-4471 for 6.0 m³, is photographed and matched to the Base B1 pour, and the pour starts at 10:35 with the chute over the formwork.

    Show the screen

    Groundworks siteSite engineer’s tablet

    Site diary

    Pour · Base B1

    Job 2417 · Plot 4 bases

    Status: Pour started 10:35

    Mix M-2 · 8.5 m³ ordered in two loads

    Tickets
    • DT-4471 · 6.0 m³Matched · Base B1
    • DT-4478 · 2.5 m³Second load
    Photos
    • Ticket DT-4471Taken 10:28
    • Pre-pour checkSigned 09:40
    • Pour startedTaken 10:35
    Log
    1. Site engineer · AK Ticket DT-4471 photographed.
    2. Site engineer · AK Ticket DT-4471 matched to the Base B1 pour: 6.0 m³.
    3. Ganger · DM Pour started at Base B1.

    The pour, with the ticket photographed and matched.

  4. Chapter 04 of 06

    Something unexpected

    Base B2 from above: the dug-out soft spot filled with light grey stone in the formation, with a groundworker kneeling at the edge and barriers behind.
    A soft spot, recorded as it was found and as it was dealt with.

    At 11:50 the ganger finds a soft spot in the formation at Base B2. The engineer photographs and measures it as found: about 1.2 by 0.9 metres.

    It is dug out 0.4 metres deeper and filled with 1.1 tonnes of stone, photographed at each stage. The engineer records it as changed-condition note CC-03, with the photos, labour and plant time, and shares it with the commercial team for their review. It is a record of what was found and done, not a claim.

    Show both screens

    Groundworks siteSite engineer’s tablet

    Site diary

    Soft spot · B2

    Job 2417 · Plot 4 bases

    Status: Shared for review

    Note CC-03 · what was found and what was done

    Shared 13:46 · Commercial team · JB

    For the commercial team’s own review. The note records what was found and done. It is not a claim.

    Photos
    • As found11:55
    • Measured11:56
    • Dug out13:10
    • Stone placed13:40
    Recorded
    Area
    About 1.2 × 0.9 m
    Extra dig
    0.4 m below formation
    Stone
    1.1 t
    Labour
    2 operatives · 1.5 h

    The changed-condition note, shared for review.

    Commercial officeCommercial team’s monitor

    Commercial · jobs

    Job 2417 · today

    Job 2417 · Tue 14 Oct

    Status: 1 note waiting

    Changed-condition notes
    • CC-03 · soft spot · Base B24 photos
    Expected today
    Daily diary
    At close
    Tickets
    Base B1 pour
    Quantities
    Concrete and stone

    The note waiting in the office.

  5. Chapter 05 of 06

    End of the day

    The tablet at the end of the day: labour and plant hours captured once, Base B1 poured with two tickets, and the diary closed.
    Labour and plant hours captured once and reused. The diary closes.

    The pour is complete at 14:20. The second ticket, DT-4478 for 2.5 m³, is matched to the same pour, and the truck leaves.

    At 16:30 the engineer closes the diary. The hours for the gang, the engineer and each item of plant are captured once and reused in the diary, the note and the office’s view. The day’s records go to the office.

    Show the screen

    Groundworks siteSite engineer’s tablet

    Site diary

    Diary · Tue 14 Oct

    Job 2417 · Plot 4 bases

    Status: Sent to the office 16:31

    Hours captured once, from the morning record

    Labour
    Ganger · DM
    07:30–17:00 · 9.0 h
    Groundworker · RS
    07:30–17:00 · 9.0 h
    Site engineer · AK
    07:30–17:00 · 9.0 h
    Plant
    D-07 Site dumper
    6.5 h
    PC-02 Plate compactor
    2.0 h
    PV-01 Poker vibrator
    3.0 h
    Today
    • Base B1 poured · 8.5 m³2 tickets matched
    • Base B2 dug to formationNote CC-03

    Reused in the diary, the note and the office view

    The diary closed, with the hours captured once.

  6. Chapter 06 of 06

    The commercial view

    The commercial team’s monitor showing note CC-03 for Base B2: four photos, the area, the extra dig, the stone, labour and plant time, marked ready for review.
    Quantities, tickets and the note arrive together, ready for the commercial team’s own review.

    In the office, the day arrives as one record for Job 2417: 8.5 m³ of concrete on two matched tickets, 1.1 tonnes of stone, the hours and one changed-condition note.

    The commercial team opens note CC-03 with its four photos, measurements, labour and plant time. It is ready for their own review. What happens next is their decision.

    Show the screen

    Commercial officeCommercial team’s monitor

    Commercial · jobs

    Note CC-03 · B2

    Job 2417 · Tue 14 Oct

    Status: Ready for review

    Soft spot in the formation, recorded on site as found and as dealt with.

    Photos from site
    • As found11:55
    • Measured11:56
    • Dug out13:10
    • Stone placed13:40
    Recorded on site
    Area
    About 1.2 × 0.9 m
    Extra dig
    0.4 m below formation
    Stone
    1.1 t
    Labour
    2 operatives · 1.5 h
    Plant
    Site dumper · 1.5 h

    Facts, photos and times. The commercial team decides what follows.

    The note with its photos, ready for the commercial team’s own review.